KEY DATES REQUIREMENTS DELIVERABLES
by June 30, 2020 submit a preliminary engineering report for the Eagle Lake – Chilson Water System Improvements Preliminary Engineering Report
by June 14, 2021 submit final map, plan, and report for the Eagle Lake – Chilson Water System Improvements Map, Plan & Report – Revised 5-17-2021
by June 15, 2022 begin final design of Eagle Lake – Chilson Water System Improvements
by May 24, 2023 submit final plans, designs, and specifications for the Eagle Lake – Chilson Water System Improvements including the construction schedule designed to achieve the final deadline of June 24, 2025 for these improvements
by September 27, 2023 advertise for bids for Eagle Lake – Chilson Water System Improvements
by November 28, 2023 award contract for Eagle Lake – Chilson Water System Improvements
by January 10, 2024 issue notice to proceed for Eagle Lake – Chilson Water System Improvements
by June 24, 2025 complete construction of Eagle Lake – Chilson Water System Improvements, and fully decommission Gooseneck Pond as a drinking water source

PUBLIC INFORMATION MEETING # DATE HANDOUTS
1
May 16, 2019
2
June 27, 2019
3
October 29, 2019
4
August 20, 2020

Upcoming Events